The new power plant is preparing to start up

The new power plant is preparing to start up

On the territory of the Lebap state power plant, construction work, installation of power plants, switchgears and commissioning work at a new gas turbine power plant, which is prepared for launch by the Japanese company Sumitomo Corporation, have been completed.

The new generating facility consists of three gas turbine units of the Japanese company Mitsubishi Hitachi Power Systems, each with a capacity of 144 MW.The project was financed by the Japanese Bank for International Cooperation through a loan agreement with Vnesheconombank of Turkmenistan.

The commissioning of the new hydroelectric power station will create the necessary technical conditions for uninterrupted power supply to the developing economy of the eastern region of the country, create new jobs, and also become the main source of electricity that will be exported to neighboring countries.

The power plant, with a capacity of 432 MW, will become the tenth generating facility built in the country since the turn of the century, with a total capacity of 6,511 MW.

The commissioning of the power plant will be another step towards the fulfillment of plans that provide for bringing the total annual volume of electricity produced in Turkmenistan to 33 billion kilowatt-hours over the next seven years.

More related articles

15.09.2020 | Development of energy industry of Turkmenistan for the interests of the country and region
15 000 tons of pipes for “Zerger” gas turbine power plant will be shipped to Turkmenistan from Russian Federation
Construction of 432MW Power Plant Completes in Turkmenistan’s Lebap Velayat
Lebap power plant is ready for launch in Turkmenistan
Increasing the energy system capacity
Expert opinion: the development of the electric power industry in Turkmenistan demonstrates high rates