Test runs of the equipment are carried out at the Euro 5 gasoline plant

At the session of the Government on April 5, Vice-premier M. Meredov informed the Head of the State about the situation at the plant for production of gasoline from natural gas, which was built in Ahal Velayat. At present moment, construction works have been completed by 96 percent while commissioning works by more than 64 percent.

Test runs of number of auxiliary installations including water treatment unit, coolers, boilers, pressurized air, air distribution and industrial water disposal systems have been accomplished. Test runs of gas treatment and synthesis units are at the final stage.

It is planned to start the commissioning of the reactor of automatic termite reforming soon, to connect methanol synthesis unit in the second decade of April and to bring the operation of the unit to designed mode within ten days.

Thereafter, the equipment for fuel synthesis will be tested.Production of synthetic fuel, which meets Euro 5 international ecological standards, is planned to be started very soon.

In addition, monitoring of construction works performed at external communications of the plant has been made.At present moment, powerline for provision of the facility with electricity has been built.

Construction and installation works have been completed at the railway coming to the plant.Laying of gravel level is at the final stage.Storage for industrial water disposal, rainwater drainage have been built.

The Head of the State ordered the Vice-premier to hold test at the plant under permanent control and to provide their relevance to international standard as well as ordered to pay special attention to training of qualified personnel for work at modern facilities of the industry.

The President highlighted that opening of big petrochemical complex would be another important step toward the diversification of the branch, creation of high technological production of good, which are on high demand in foreign markets.

Speaking of the labelling used by the structures of fuel and energy complex, the Head of the State noted that it has meet international labelling system used in the world. advanced practice and modern tendencies has to be used as a guidance during development of the system.

More related articles

The first day of the International Conference “Oil and Gas of Turkmenistan 2024” has ended in Ashgabat
Turkmenistan to Launch Production of Data Storage Server Equipment
Turkmenistan to Build Underground Gas Storage Facilities
20.02.2018 | Chronicles 2017: Agricultural Complex
Chronicles 2017: Agricultural Complex
24.10.2018 | New railway loading faciltiy of Kenar Oil Terminal is put into operation
Automatic railway loading facility is put into operation at Turkmenbashy Refinery Complex